CLIENT : CI-ENERGIESPERIOD: September 2017 to April 2018
FUNDING : CI-ENERGIES / World Bank (WB)COUNTRY : Ivory Coast

SUMMARY OF THE MISSION

Having signed a US$325 million loan agreement, Côte d’Ivoire intends to finance the Electricity Transmission, Distribution and Access Project (PTDAE), which aims to increase access to and improve the quality of electricity facilities in the country.

Within the framework of the PTDAE, BPL was entrusted with the realization of an environmental and social impact assessment and the RAP of the Extension and reinforcement of the distribution networks of the commune of MAN, one of the ten (10) regional capitals of Côte d’Ivoire benefiting from the project.

The services provided by the consultant as part of this mission include:

  • Identification of existing sensitive elements in the project environment;
  • Determination of project activities likely to have an impact on the environment;
  • Collecting the opinions of project stakeholders and the expectations and concerns of the populations likely to be affected;
  • Conducting community consultations and public consultations;
  • Identifying, analyzing and evaluating the significance of potential impacts of the project;
  • The proposal of recommendations for the mitigation of negative impacts and the improvement of positive impacts;
  • The preparation of an ESIA report and the development of an Environmental and Social Management Plan (ESMP);
  • The realization of a Resettlement Action Plan (RAP) report.